Competitive dialogue procedure for construction contracts
The European Union Procurement Directives establish public procurement rules throughout the European Union and apply to any public purchases above the defined thresholds. The purpose of the directives is to open up public procurement within the European Union and to ensure the free movement of supplies, services and works. The directives are enacted in the UK by The Public Contracts Regulations. Public projects must comply with the regulations if the value of contracts is above specified thresholds.
The Public Contracts Regulations allow four procurement procedures:
- Open procedure. There is no pre-qualification process or short-listing process. Anyone that responds to the OJEU notice is issued with the full contract documentation.
- Restricted procedure. There is a pre-qualification process, and only short-listed candidates are invited to tender.
- Competitive dialogue procedure. There is a pre-qualification process. Short-listed candidates are invited to take part in a dialogue process during which the nature of the project may be discussed and possible solutions may be developed. When the dialogue process is complete, final tenders are invited.
- Competitive negotiation procedure. There is a pre-qualification process. Short-listed candidates are invited to take part in a negotiation process. The negotiation process does not have to follow any particular rules, and has no formal ending. This means that negotiations can continue even after the preferred bidder has been appointed.
Use of the competitive negotiation procedure has been questioned as it is thought that extended negotiations with a preferred bidder may impact upon the competition. It is for this reason that the competitive dialogue procedure was introduced and guidance was issued by the Office of Government Commerce (OGC) stating that the competitive negotiation procedure should only be used under ‘...very exceptional circumstances’ (ref OGC: Guidance on the competitive dialogue procedure in the new procurement regulations, 2006).
The regulations state that the competitive dialogue procedure should only be used on ‘particularly complex contracts’ where:
- The client cannot define the technical means for satisfying their requirements.
- The client cannot define the legal or financial make-up of the project.
- Using the restricted or open procedure would not be possible.
Where a competitive dialogue procedure is to be followed, it is recommended that the reasons for adopting the procedure should be formally recorded. The procedure that will be followed should then be described in the contract notice, after which that procedure must then be followed.
This process of dialogue is intended to identify the solution most likely to satisfy the clients needs. This process is likely to require a considerable commitment of resources by both the client and the bidders.
The dialogue process can be used to progressively reduce the number of bidders.
As changes to the nature of the project are restricted after the dialogue process, the client may wish to request a fully-developed draft bid from bidders before they formally conclude the dialogue process and invite final tenders.
Concerns have been raised about the cost and time required to take part in such a procedure, as proposals have to be developed more fully before the award of the contract than they would have done under a competitive negotiation procedure. There are also concerns about the difficulties of protecting intellectual property and other confidential information during the dialogue process.
[edit] Related articles on Designing Buildings Wiki
- Competitive procedure with negotiation.
- Construction contract.
- Contract conditions.
- Invitation to tender.
- Negotiated Procedure without Prior Publication NPwPP.
- OGC.
- OJEU.
- PFI.
- PF2.
- Procurement route.
- Public procurement.
- Tender documentation.
- Tender process.
[edit] External references
- Practical Law: The competitive dialogue procedure … so many questions.
- HM Treasury: Guidance on competitive dialogue.
- The Public Contracts Regulations.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.